Due to unforeseen circumstances, the construction timeline along Centre Ave in Cochrane has been extended.

"While completing the required work, the contractor encountered a third-party utility conflict involving ageing infrastructure," reads a statement from the Town Of Cochrane.

"We are working with the project team to assess the extent of this impact and will provide you with an update when available."

"We currently anticipate the full opening of Centre Avenue will not be until the end of the month, weather permitting."

Earlier this month, three of the four directions of the First and Centre intersection reopened to motorists after a month-long closure due to construction.